Pollution Control Retrofit
Captive power plant · Chhattisgarh
Utility-scale boiler, ESP system
- Problem
- ESP efficiency degraded below emission norms after years of service
- Constraint
- Outage window fixed by plant's annual maintenance schedule
- Scope executed
- ESP field upgradation and internals replacement
- Control system retrofit
- Performance guarantee test
- Outcome
- Emission levels restored within statutory limits, confirmed by performance guarantee test
- Documentation delivered
- R&M engineering package
- Performance guarantee test report
- As-built documentation
- Duration
- 6 weeks
- Team size
- 15 technicians, 2 site engineers