24×7 breakdown desk+91 90000 00000
Svedha Engineering

Boiler Repair

Integrated paper mill · Gujarat

Water tube boiler, 45 TPH, 18 years old

Problem
Repeat water wall tube leaks forcing unplanned trips roughly every six weeks
Constraint
No standing shutdown window — repairs done during 18-hour planned trips only
Scope executed
  • Multi-tube water wall section replacement
  • In-situ NDT to rule out adjacent tube thinning
  • Refractory patch repair around the affected zone
Outcome
Zero unplanned trips in the following two quarters; boiler returned to service within the 18-hour window each time
Documentation delivered
  • NDT records
  • Material test certificates
  • Welder qualification records
Duration
18 hrs per trip, 3 trips
Team size
6 technicians, 1 site engineer
More on Boiler Repair