Boiler Overhaul

Textile processing plant · Gujarat

Fire tube boiler, 8 TPH, 12 years old

Problem
Boiler licence renewal due with heavy fireside scaling reducing efficiency
Constraint
5-day annual shutdown window, fixed by production calendar
Scope executed
  • Full strip-down and mechanical de-scaling
  • Hydrostatic test
  • Licence renewal inspection preparation and liaison
Outcome
Licence renewed with no observations; measured efficiency recovery of several percentage points against pre-overhaul baseline
Documentation delivered
  • Hydrostatic test certificate
  • De-scaling report
  • Licence renewal correspondence
Duration
4 days
Team size
8 technicians, 1 site engineer